To change status from the Search Tasks page:
- Select the checkboxes to the left of the PM Task (or group of PM Tasks) to make a status change.
- Click the Actions dropdown and select Change Status:
- If changing the status to Complete, an option will be provided to manually set the completion date and time.
- Change the work order status, add a comment if applicable, and click SAVE.
To change the status from within a specific PM Task:
- Click CHANGE STATUS:
- If changing the status to Complete, an option will be provided to manually set the completion date and time.
- Change the work order status, add a comment if applicable, and click Save