If a problem is discovered with a piece of equipment and an open PM task does not exist, an unscheduled task can be created from the equipment record.
To create an Unscheduled Task:
- Click Go To > Preventative Maintenance > Equipment Search.
- Use the SEARCH or column filters to locate the desired piece of equipment.
- Select the piece of equipment from the search grid.
- Click the TASKS tab.
- Click , and select New Unscheduled Task.
- Enter a NAME for the task, select an ASSIGNEE, and enter the number of days allotted to complete the work. Additional task notes can be entered in the NOTES field.
- Click SAVE.